A Phase I ESA typically takes about two weeks from order to final report. Breeze delivers in about 10 days as standard, or about 5 days with rush delivery. The exact timing depends on site access and how quickly local agencies respond to records requests.
What happens during those 10 days
- Day 1: your project manager confirms scope, lender requirements and site access.
- Days 1–5: database reports, historical maps and aerials are pulled, and records requests go out to local agencies.
- Days 2–6: a local field professional completes the site visit and interviews.
- Days 6–10: the Environmental Professional reviews everything, writes the findings and signs the report.
What causes delays
- Waiting for access to locked buildings, tenant spaces or rooftops
- Slow responses from municipal, fire or health departments
- Properties with long industrial histories that need extra research
- Late user questionnaire or lien search information
Ordering as soon as the property is under contract is the simplest way to protect your closing date.
How long a Phase I is valid
Under All Appropriate Inquiries and ASTM E1527-21, a Phase I has two important time limits:
- 180 days: the interviews, lien search, government records review, site visit and EP declaration must each be completed within 180 days before the date you acquire the property.
- One year: the report is generally considered viable for up to one year, provided those components are updated if they're older than 180 days.
After one year, you generally need a new Phase I. Lenders may have their own rules too: SBA lenders, for example, generally need reports dated within one year of the SBA loan number being issued.
Updating an existing report
If a Breeze Phase I is less than a year old, we can usually update the time-sensitive components rather than starting over, which is faster and less expensive. Call us with the report date and your closing date.
Frequently asked questions
How fast can I get a Phase I?
Breeze delivers standard Phase I ESAs in about 10 days and rush reports in about 5 days.
Is a Phase I good for one year?
Generally yes, as long as the time-sensitive components are within 180 days of your acquisition date or are updated. After one year a new report is usually needed.
This article is general information about environmental due diligence and is not legal advice. Requirements can change; confirm specifics with your lender or attorney.